1/19/2009 looking east along the path near new Cottleville City Hall
Dardenne Greenway Cottleville SEED Trail- Phase I
Description of Work: Asphalt Path & Bridge Installation
ICR Scope: Construction Manager
Projected Schedule: January – March 2009
National City Bank- Page & Grand
Description of Work: Retail branch construction
ICR Scope: Tenant Build-out of National City Bank
Projected Schedule: April – May 2009
Lambert Airport Upgrades to Mechanical Systems
Description of Work: Upgrades to HVAC Systems on multiple terminals
ICR Scope: Demolition & Concrete Work
Projected Schedule: ICR Complete February 2009